Before the task has been started you may change all task specifications by
•      
selecting 
  Change  
  Properties  
in the action menu of the task. The action form contains all sections that we 
have described above where you may 
correct your specifications.
You may also change certain specifications directly by 
calling e.g. 
  Change  
  Input  
when you want to correct the input data fields. If you want to delete the 
deadline of a task (e.g. using 
  Change  
  Deadline ) 
you have to enter an empty date. 
Once a task has been started, the task specifications that 
may be changed depend on the state of the task (an overview of the states of a 
task is given in 8.1.8 Handling exceptional task 
situations). In states where the task may be started again, all 
specifications may be changed. In other states, some specifications may still be 
changed, e.g. in state requested you as requestor may request additional 
results by entering further output data, but you may not change the input data 
or the contractors. The action form ‘Change task’ offers all changes 
that are possible in the current state of the task as do the specific actions 
offered in the 
  Change  
menu.